Skip to content

Simulate plant operation

A plant simulation reconciles supply and demand for each hour of a modeled year. It reports component output, battery operation, fuel use, unmet demand and economic results from that dispatch.

This is a single-bus energy model. Use a separate network study to calculate bus voltage, branch loading and electrical losses from network impedances.

Run a baseline

  1. Open Design and select the intended design and version.
  2. Confirm the selected load profile, its reference scale, weather channels, enabled components and dispatch strategy.
  3. Read the build notes and correct blockers. Review assumed costs even when they do not stop the run.
  4. Leave Search for a cheaper size off to test this configuration.
  5. Use the simulation action. Its accessible label is Save a version and simulate it for a changed draft, or Simulate this version for an unchanged saved version.
  6. Wait for the named run to complete. Open Results and confirm its design, version and run identity.

Live preview is optional. It simulates a year after settled edits but does not create the named run that serves as the saved record. Use a completed named run for comparison and reporting.

Read results in order

Results tabWhat to examine
ReportThe verdict, annual supply, reliability and cost summary.
Time seriesThe month, week or day where an operating concern occurs.
ConsoleReplay of computed hourly operation and component flows.
DispatchWhat each source delivered, how long it ran and what it consumed.
EconomicsComponent cost across the modeled project life.
Cash flowRecorded yearly amounts.
AssumptionsInput values, provenance and unresolved source gaps.
SolutionsScored sizing alternatives when the selected result comes from a search.

Start with unmet demand and feasibility, then examine cost. Identify whether a value is zero, absent because the component is not installed, or unavailable from this result. These states do not mean the same thing.

Inspect a difficult hour

Find an interval with unmet demand, low battery state of charge or heavy generator use. Compare demand with available solar/hydro, generator and grid supply. Check battery discharge power as well as stored energy. A large kWh capacity cannot remove a converter power limit.

For diesel operation, check the selected dispatch strategy, allowed loading and charging thresholds. A cycle-charging strategy needs a battery. Explain the operational reason before switching strategies.

Recover from a misleading view

If results appear inconsistent with the editor, check the run identity first. The editor can show a newer draft or version while the result still belongs to an older run.

If a chart is blank, check that the run completed and inspect its tables. Do not interpret a missing plot as zero output. The September 2026 screenshot review found blank plots in one development capture; those captures are not used as evidence of a complete time-series view.

Keep a reproducible record

Retain the design version, run identifier, demand declaration, weather provenance, dispatch settings and assumptions with any exported report or workbook. A console image shows a modeled hour, not live plant telemetry.

Continue with Sizing and optimization, or Plant to network. This guide describes the inspected development workflow; confirm release compatibility.